The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as

Accounting | Auditing | Commerce | Economics | Finance | Law | Statistics | Taxation | PMT

Q. The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as
(A) resource assignment
(B) resource leveling
(C) resource splitting
(D) resource scheduling

The answer is: (B) resource leveling