In project management, which of the following is NOT a method of reducing the impact of an unexpected event?

Accounting | Auditing | Commerce | Economics | Finance | Law | Statistics | Taxation | PMT

Q. In project management, which of the following is NOT a method of reducing the impact of an unexpected event?
(A) Risk avoidance
(B) Risk sharing
(C) Risk transfer
(D) Risk elimination

The answer is: (D) Risk elimination
The project team can reduce (but cannot eliminate) risk in various ways including risk avoidance, risk transfer, risk reduction, and risk sharing.