11. The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as
(A) resource assignment
(B) resource leveling
(C) resource splitting
(D) resource scheduling

12. A horizontal bar chart that shows project tasks against a calendar is called
(A) milestone
(B) goal
(C) Gantt chart
(D) PERT chart

13. The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as
(A) milestone
(B) goal
(C) Gantt chart
(D) PERT chart

14. Which of the following statement(s) is/are true about a Project?
I. It brings change
II. It has risk
III. The outcome is certain
(A) I only
(B) II only
(C) I and II only
(D) I, II, and III

15. Which of the following is NOT a part of project management?
(A) initiating
(B) monitoring
(C) closing
(D) All above are parts

ANSWERS: PROJECT MANAGEMENT MCQ
11. (B) resource leveling
12. (C) Gantt chart
13. (D) PERT chart
14. (C) I and II only